Infrastructure ENERGY

Kariba South Extension Project's first unit will be commissioned by end December 2017

www.zimtreasury.gov.zw December 7, 2017
Achieved
Jan 2018

Kariba South to the rescue

www.sundaymail.co.zw January 14, 2018

Zimbabwe’s electricity challenges have eased following injection of 150 megawatts into the national grid upon completion of Phase One of the US$355 million Kariba South Hydro-Power Station Expansion project.